DIFC Ruling: Notice Compliance & Delay Analysis

A recent ruling by the DIFC Court (Dubai International Financial Centre Court) has highlighted the critical role of notice provisions in construction contracts. The case was Panther v. MESC, which involved a project delay, rejected extension of time (EOT) applications, failed negotiations, and contract termination. The court’s decision not only sheds light on the interpretation of contractual clauses but also underscores the significance of complying with notice requirements and reliance upon retrospective delay analysis using AsPlanned Vs As-built methodology instead of prospective analysis using Time Impact Analysis methodology. Contractors and employers across the GCC and beyond should take note of the implications of this ruling.

The Court also recognized that in undertaking the As-Planned vs As-built analysis, the MESC’s Delay Expert:

The court declared that the analysis presented by the Panther’s Delay Experts was significantly less reliable than that of MESC’s Delay Expert because they did not conduct any independent analysis to verify what was the correct critical path but instead considered the pleaded delay events in the light of the contemporaneous updated programmes.

Frequently Asked Questions

Get answers to frequently asked questions about everything we do.

What is the main focus of this eBook?

This eBook analyzes a significant DIFC Court judgment in the Panther v. MESC case, highlighting the critical importance of notice compliance under FIDIC contracts and the appropriate use of delay analysis methods—especially retrospective (As-Planned vs As-Built) over prospective (Time Impact Analysis).

We use cookies to enhance your experience. By continuing to visit this site you agree to our use of cookies.